Underground Cable Laying Method Statement
Trench Excavation WorksMethod of Cable Pulling & LayingCable Testing & CommissioningSet out and mark the exact line of cable route as per approved drawings and the obtain NOC/ Permission to Work. Excavation is carried out using a mechanical excavator. In areas where usage of excavator is unsafe / not possible, the trench is made through manual digging. As per requirement of project specifications, where sand dunes or any See more on electricalengineering123 SlideShare
Fiber Optic project implemetation procedure | PDF - SlideShare
See MoreThe document outlines 10 stages of a fiber optic cable installation project: 1. Proposed route survey using GPS and mapping software. 2. Drafting an AutoCAD drawing of the survey. 3. Trenching